February 17, 2026
Dear Campus Community,
Please be advised that the southbound lane on Gayley Rd. will be closed once per week between February 25, 2026 and April 21, 2026, to support scheduled concrete pours.
Please refer to the attachment for details. Traffic Control Schedule for SB Lane Closure:
| Date | Time |
| Wednesday, February 25, 2026 | Midnight to 8:00 AM (A&B work 8:00 AM–4:00 PM) |
| Tuesday, March 3, 2026 | Midnight to 8:00 AM (A&B work 8:00 AM–4:00 PM) |
| Tuesday, March 10, 2026 | 6:00 AM to 2:00 PM |
| Tuesday, March 17, 2026 | 6:00 AM to 2:00 PM |
| Tuesday, March 24, 2026 | 6:00 AM to 2:00 PM |
| Tuesday, April 7, 2026 | 6:00 AM to 2:00 PM |
| Tuesday, April 21, 2026 (Pads) |
6:00 AM to 10:00 AM |
This work will not impact key campus events, including Cal Day (4/18/26), Commencement (5/16/26), or performances at the William Randolph Hearst Greek Theatre.
Please do not hesitate to contact Iman Rad, Senior Project Manager, at +1 (310) 404-1852 if you have any questions or concerns. Visit cumming-group.com for more information.
Traffic Control Plan